Service Entrance Ready for Paving

The service entrance to the east side of the new parish hall addition is almost completed. This roadway, which will not connect with the parking lot at the rear of the church, will be for use by the garbage contractor and for emergency access by the Fire Department. A stub road will be created where the parking circle used to be outside the parish offices, so that trucks can turn around before entering Kings Road. The upper portion of the service road, by the existing Nieman Hall where the garbage dumpsters will be located, has received a base coat of paving. The lower portion was disrupted by the need to install a new electric service, and on Friday, October 24, was being prepared for paving.

Photo by Will Vandeveer