Thursday, July 31, 2008
Filling the Hollow Blocks
No Job for an Amateur
Testing Our New Water Main
Wednesday, July 30, 2008
Big Drainage Project
Out Go the Kitchen Windows!
Tuesday, July 29, 2008
The Walls Are Growing!
Another Load of Concrete Blocks
No more flooding?
Kit Cone
Monday, July 28, 2008
Progress as of July 26 (continued)
There is tremendous progress with the construction of the new addition at the rear of the church. Concrete block walls are going up at a great rate.
Blocks are stacked on scaffolding by laborers, so that masons can pick up the next block and set it in place with minimal "running around" for supplies.
A long-standing drainage problem at the back of the church should be remedied by the installation of a very generously designed storm water runoff system. In the photo above, new PVC drain pipes for the addition are visible prior to being buried, and at right are the visible parts of a new eight-inch drain system for the existing building. In the photo below, drain pipe is stacked at the ready to be installed from roof drains at the side of the old rectory, feeding directly into the new drain under the former exit driveway down to Kings Road. The remediation work, being done as part of the new construction project, should eliminate the frequent flooding of the courtyard outside the Chapel of the Epiphany and the Madison Day Care Center classrooms.
Progress as of July 26
Excellent progress! The former exit driveway has been excavated in recent weeks to lay new drain and water supply pipes. As this work nears its completion, the lower portion of the driveway has been restored to grade. The photo above is looking up the driveway from Kings Road; the photo below is taken from the top of the driveway looking toward Kings Road.
It has not been possible to make pictures inside the building during the removal of asbestos. This work continues, but the contractor has cleared the site of any asbestos, and Sunday services were held in the church as usual. The photo above is the familiar "old way" of entering the church, from the "main door" between the kitchen and the choir room. The asbestos floor tiles have been removed, and hall looks very stark and bare. The photo below shows the contrast between the original light green color of the floor in Nieman Hall and the present dark green; the difference was caused by 50 years of wax buildup.
Friday, July 25, 2008
Progress as of July 25
A deep trench where the former exit driveway used to be is being backfilled today, following the installation of storm drains, sanitary sewer line, and a new six-inch water main to feed the new fire sprinklers. Sprinklers are being installed in the basement of the existing church, and throughout the new addition.
Masons are moving quickly with the construction of the basement walls in the new addition. In places where they join the existing part of the church, the concrete blocks must often be cut to fit; the cloud of dust at left center is churned up by a diamond-tip saw cutting a block. The open space at the back right of the foundation is a temporary access route for the skid-steer bucket loader, the small red vehicle at center right, so it can enter the "basement" to bring in more concrete blocks.
Two of the many masons on the job are shown placing concrete blocks adjacent to the existing building. The concrete blocks are built up on top of the poured concrete foundation, and locked together by reinforcing rods set into the footing.
Grace Church is now open for the weekend of July 25-27
Tuesday, July 22, 2008
Work in the front yard for the new water main
These photos show the work in the front yard. Although most of the visible work at this time is in the back of the church, where the major construction is under way, there is also a lot of earth-moving going on in front.
An excavation for a six-inch water main has been completed, and the pipe put in place. It will feed the new fire sprinkler system in the basement of the present church and in the new addition.
Signs of progress: the Rector can park in her driveway again!
This picture shows a very appreciated kind of progress: the rectory has its new driveway! After a long time tramping through the construction work to get to her house, Lauren can now park in the driveway just like a real suburbanite! Welcome home, Mother Lauren!
How tall do they think Grace parishioners are???
Some photos taken by Kit Cone yesterday, the first day of the Hazmat work, with his notes:
This is the asbestos warning sign in the back door of the church......which you would have to be 15-20 feet tall to even read!
The third picture shows the placement of a lot of concrete block today. The masons were really busy! And notice that the reinforcing rods have to poke up in precisely the right place to line up with the holes in the concrete blocks! Then they pack the hole in the block with concrete to make sure that this building will last longer than forever!And on the first day of operations, the asbestos removal fellows set off the fire alarm. Fortunately Captain Ed was able to resolve the problem, which was in the alarm rather than any fire in the building. The inside of the building is absolute chaos, with doors covered by heavy plastic taped in place.
In response to some conjecture about whether anyone could go in the building during the asbestos removal: NO!
Saturday, July 19, 2008
Signs of progress: the new parish hall foundation has been poured
Kit Cone, who took the above photo, wrote:
Today the concrete for all the footings under the new addition was poured in one day! The photo shows the concrete mixer putting the last load into the forms. (Earlier in the day a concrete pump had been used, but at that point I was on the road with the Recycling Ministry on a four-shift day!) The "fence" sticking out of the newly poured concrete footings is reinforcing rod which will bond the next layer of concrete to the footings. The footings themselves are also heavily reinforced with the same kind of steel rods.
Friday, July 18, 2008
Driveway & parking lot access this weekend, July 19-20
Remember that parking on the circle via the old exit driveway is no longer possible, while they work on the widening and drainage issues.
Grace Church closing for Hazmat work - UPDATED
Services, events and meetings will be relocated as follows:
- Weekday services will be held in a temporary chapel in the Rectory.
- Saturday and Sunday services will be held in the church as usual.
- The “Saving Jesus” Series on Wednesday evenings will be held at the home of Jim & Sue Van Leuven in Madison.
- The Finance Meeting on Monday, July 21 has been canceled. The next meeting will be Monday, August 18. In the interim, chair Elizabeth Vandeveer will email information to committee members as necessary.
- The Craft Guild which meets on Tuesday evenings will be held at the home of Joyce Alexander in Madison on July 22 and 29. No decision has been made yet about the August 5 meeting; please speak to Jaclyn Connell for more information.
Wednesday, July 16, 2008
Exit driveway and circle closed
Needless to say, parking on the "circle" is no longer possible. Luckily, the main driveway and parking lot are fully accessible.
Tuesday, July 15, 2008
Signs of progress: preparing to pour foundation
Grace Church closed for Hazmat work starting Monday, July 21
Services, events and meetings will be relocated as follows:
- Weekday services will be held in the living room of the Rectory, which will be converted into a temporary chapel.
- Saturday and Sunday services will be held in the church as usual.
- The “Saving Jesus” Series on Wednesday evenings will be held at the home of Jim & Sue Van Leuven in Madison.
- The Finance Meeting on Monday, July 21 will be held in an alternate location to be announced. Please speak to Mother Lauren or Elizabeth Vandeveer for more information.
- The Craft Guild which meets on Tuesday evenings will either relocate or go on hiatus. Please speak to Jaclyn Connell for more information.
Friday, July 11, 2008
Now it's a REALLY HUMONGOUS hole!
Kit Cone demonstrating the size of the really humongous hole.
Please observe the orange fencing and yellow caution tape, and keep a safe distance.
Driveway & parking lot access this weekend, July 12-13
A very nice touch: Visbeen Construction has placed a row of hay bales around the dirt piled temporarily at the back of the parking lot. Knowing that we need to keep the parking lot accessible and tidy for church services, Visbeen wanted to keep any mud from running off the piles onto the pavement in a rainstorm. So they went the extra mile and put the hay bales in place.
Signs of progress
Fire sprinklers are being installed in the classroom area of the church basement as part of the construction project. A new six-inch water main will be installed from the street to the building to supply the fire sprinklers. An automatic alarm will summon the Fire Department in the event that the sprinkler system is activated.
Tuesday, July 8, 2008
That's a BIG hole!
Artifacts from the past, unearthed
Some of the many very old bottles found by Jim Alden in one of the piles of dirt dug up in preparation for the construction. These bottles were just sticking out of the pile. Very likely a search would disclose hundreds more! Many are old milk bottles from local dairies, and some appear to have held liquor, but we don't yet know why they were buried on the church grounds.
Monday, July 7, 2008
Excavation begins for new parish hall foundation
Watch that first step - it's a doozy! (This is why we can no longer use the back door.)
And this is why there's no Mass on the Grass this summer.


Additional parking behind Grace Counseling Center
Thursday, July 3, 2008
Driveway & parking lot access this weekend, July 4-6
The back parking lot can be used. Just be aware that the lines delineating parking spots are somewhat obscured by dirt.
The side lot for staff/handicapped parking (across from the side door) can also be used. In order to allow enough room for two-way traffic, please park parallel to the retaining wall (as the truck below is doing), NOT head-in. There should be room for three cars in this area.
Remember that you can always use the new, additional parking lot behind Grace Counseling Center, next door to Grace Church.


